BARAS FLOOD CONTROL

Print

Baras Flood Control

Municipality / Province : Baras, Rizal
Actual Project Cost : Php 10,000,000.00
Project Completion : 2010

The flood control structure shall be built on the last half kilometer segment of the river. An embankment with an estimated average elevation of 2.5 meters from the riverbed shall be constructed. Gabions shall be used as the embankment material on the riverside and lakeside while vetiver grass shall be employed to stabilize the filled earth on the landside.

Boat mooring areas shall be provided along the river and lake. These shall have gaps to allow fishermen to gain access to the adjoining barangay road.